Planning and building

Building Control

Building safety regime

New Building Regulations came into force on 6th April 2024, implementing the requirements of the Building Safety Act 2022. Here's what you need to know about the new regulatory regime.

In August 2023, the Government published secondary legislation importing the new regulatory regime for building and design work anticipated by the Building Safety Act. A six-month transitional period was introduced to allow the industry to catch-up with the changes and to exempt some existing projects from the scope of the new regime.

The new regulatory regime came fully into force 6 April 2024. Therefore, social landlords undertaking new building or design works need to operate under the new rules, with strict penalties for those who don't comply.

 

Building Safety Regulator

The Act establishes the Building Safety Regulator, located within the Health and Safety Executive, with responsibility for all buildings in England. The Regulator has a broad range of powers to regulate the built environment and will also prosecute breaches of the Building Safety Regime.

From 6 April 2024, the Regulator became the Building Control Authority for all new and existing "Higher-Risk Buildings" (HRBs). These are defined as residential buildings that are at least 18 metres or seven storeys tall (measured from ground level) and containing at least two residential units. Care homes and hospitals meeting these height requirements will be HRBs for their design and construction phase.

Top of page


Duty Holders and competency requirements

The Building Regulations etc. (Amendment) (England) Regulations 2023 establish new Duty Holder roles in respect of most building work and design work covered by the Building Regulations 2010 and commencing after 1st October 2023.

The Duty Holders roles replicate the existing CDM Regulations roles of Client, Principal Designer, Principal Contractor, Designer and Contractor, though these roles are additional to the CDM obligations. Social landlord clients undertaking building work and design work must appoint a Principal Contractor and Principal Designer for the work, ensure that these and other appointees are "competent", as defined in the new legislation.

Top of page


Gateways regime for higher-risk buildings

Social landlords commissioning new HRBs ("HRB Work") or undertaking major works to existing buildings ("Work to Existing HRBs") are required to comply with the three-stage Gateways regime set out in the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023.

  • Gateway 1, which has been in force since August 2021, requires the submission of fire safety information as part of planning approval applications for HRB projects.
  • Gateway 2 requires the Client (or someone on its behalf) to submit a Building Control Approval Application to the Regulator, setting out detailed designs and method statements for the project and details of key appointees. The Regulator has 12 weeks to determine any HRB Work application and 8 weeks for work to Existing HRB applications and may approve applications unconditionally or subject the completion of specified requirements. Relevant projects must not commence until approval has been granted, and any projects commencing without approval will be an offence under the Building Act 1984 (as amended).

During the Construction Phase, the Client and Principal Duty Holders must establish a digital facility for the storage of Golden Thread Information; a Mandatory Occurrence Reporting System for the reporting of safety occurrences on-site; and a Change Control log. Key changes to the project classified as "Notifiable Changes" must be notified to the Regulator before the change can be undertaken. Significant changes classified as "Major Changes" must be approved by the Regulator before they can be undertaken.

Following completion of the works, the Client or someone on its behalf must submit a Gateway 3 application, now called a "Completion Certificate Application", setting out final as-built drawings and completed versions of the documents submitted at Gateway 2, together with statements from the client and principal Duty Holders that the project is compliant with the Building Regulations. The Regulator has 8 weeks to determine Completion Certificate Applications, which again may be approved unconditionally or subject to fulfilling specified requirements.

Top of page


In-occupation obligations for higher-risk buildings

Following the issue of a Completion Certificate, the owner of the common parts of the building (the "Accountable Person") or the exterior of the building ("Principal Accountable Person") will become legally responsible for managing safety risks in that building for its entire occupation period.

For newly built HRBs, the Accountable Person must register the building with the Regulator before the building can be legally occupied. Occupation of an unregistered building will be an offence under the Building Safety Act, except where partial occupation was approved as part of the Gateway 3 application.

Existing HRBs were required to be registered with the Regulator by 1st October 2023. The Regulator has announced plans to "call in" all existing HRBs to be registered over the next 5 years.

Top of page


What to do next

The new regulatory regime will require social landlords to rethink the procurement, planning and management of most building and design work undertaken in respect of their properties. Non-compliance with the rules will now be an offence, and individuals within organisations may also be held liable for breaches of the rules.

Given the high stakes, social landlords should familiarise themselves with their obligations and ensure that the relevant requirements are being met.

Top of page


Anticipated changes

Building Safety will undoubtedly continue to dominate the construction landscape during 2026 as the Government seeks to accelerate the pace of remediation of buildings with unsafe cladding, following the Grenfell Tower fire in 2017:

  • There are number of important appeal cases will be heard in 2025/2026 and are expected to lead to clarification of some provisions of the Building Safety Act 2022 (“BSA 2022”).
  • The Building Safety Levy expected to be introduced in Autumn 2026.
  • Greater Government focus on the delivery of remedial schemes for buildings requiring remediation with the Government’s Remediation Acceleration Plan
  • Planned legislation to regulate buildings between 11 metres and 18 metres and legislation on the safety of vulnerable persons within Higher-Risk Buildings.
  • Implementation of the Phase 2 Grenfell Report Recommendations.

From 30th September 2026 there will be a new requirement for a second staircase in blocks of flats of 18 metres or greater, subject to transitional provisions. Expect to see this being factored into new buildings in the planning and development phase in readiness for those provisions taking effect.