As part of the Access York project three new Park & Ride sites (Askham Bar, Poppleton Bar, Clifton Moor) are proposed to improve the existing service.

Approval was gained to progress the sites in March 2010 however this was suspended by the new government in June 2010.

A new Best and Final Funding Bid for two of the sites (Askham Bar and  Poppleton Bar (A59)) was submitted to the Department for Transport (DfT) on 9 September 2011.  Alternative ways of delivering the Clifton Moor site are being investigated.

The Department for Transport granted funding for the new Poppleton Bar site and the replacement Askham Bar site on 29 November 2011. Total cost of the project is £21.9m with funding approved on the basis of a 70% DfT and 30% City of York Council split.

The sites have received planning approval subject to conditions. The designs for the sites and associated highway works are now being finalised. Following tendering of the work and final approval by the Department of Transport it is expected that construction will commence in early 2013 with the two sites opening in spring/summer 2014. Latest details and layout drawings are included in the separate site sections below.

If you would like to receive email updates on the Access York project please email accessyork@york.gov.uk